Estimate a ready-mix order from a quote
Enter your concrete volume and the supplier's price per cubic yard or cubic meter. Add any allowance, order increment, total delivery charge, short-load fee and other quoted charges. All money inputs and outputs are US dollars. Starting prices are examples, not current market quotes.
Cost formula and worked example
Required volume = base volume × (1 + allowance / 100). With an order increment, order quantity = round up(required volume / increment) × increment. Enter an increment of 0 to use the required volume directly.
Concrete cost = order quantity × quoted unit rate. Subtotal = concrete + delivery + short-load fee + other charges. Tax estimate = selected taxable basis × tax rate / 100. Total = subtotal + tax.
Example: 5 yd³ plus 5% allowance gives 5.25 yd³. An order increment of 0.25 yd³ leaves the order at 5.25 yd³. At an example rate of $165/yd³, concrete costs $866.25. Add $100 total delivery with no other charges or tax: estimated order total = $966.25.
Match the volume unit to the price unit
You can enter the project volume in cubic feet, cubic yards or cubic meters. The calculator converts it to the price and order unit internally. 1 yd³ = 27 ft³ = 0.764554857984 m³. Changing a selector keeps your numeric entries, so choose the units that match the measurement and supplier quote. Rate and order increment always use the same selected price unit.
Allowance and order increments
An allowance increases the required volume before order rounding. The starting 5% is editable. When copying a total that already includes waste from another calculator, use 0% here. Enter your supplier's actual order increment or 0 if none applies. Confirm any minimum order separately; this calculator does not impose a minimum.
Example: 5.1 yd³ with 0% allowance and a 0.25 yd³ increment rounds up to 5.25 yd³. The added 0.15 yd³ is charged at your quoted concrete rate. Exact decimal arithmetic keeps a quantity already on an increment from rounding up to another increment.
Enter total quoted delivery and fees
Delivery, short-load and other charges are flat totals for the entire order. If a quote charges per load, first total the applicable loads and enter that amount. Enter 0 where a fee does not apply. The tool does not infer short-load charges, truck capacity, fuel surcharges, waiting time or returned-concrete fees.
If pumping or another service should be included, enter its quoted amount in Other order charges. Labor, forms, reinforcement and finishing are outside this ready-mix order estimate.
Tax and money rounding
Use only a tax rate and basis confirmed for your quote. Choose either Concrete only or Entire subtotal. If your situation needs a different taxable base, leave the rate at 0% and calculate the applicable tax separately. Use 0% when your entered prices already include tax.
Concrete cost rounds to the nearest cent, with half cents rounding up. Fees accept cents. Subtotal is the sum of those displayed amounts; tax rounds to cents and then adds to the subtotal. The displayed breakdown therefore adds to the displayed total. Volume displays use three decimals, while the calculations retain the entered precision.
Confirm the final order
Use the mix specification, delivery schedule, quantities and charges agreed with your supplier. This is a planning estimate from your inputs and does not create an order or obtain a quote.